400kV HV overhead line to the Totana ADIF traction substation (Murcia)
Type of work:
T&D
Clients:
Spanish Railway Infrastructures Administrator (ADIF)
Location:
Spain

400kV HV overhead line to the Totana ADIF traction substation (Murcia)

The scope of this contract includes both the supply of materials and the installation of a 400 kV dual phase power line, consisting of two sections:

  • Single circuit, 1.8 km.
  • Dual circuit, 10.7 km.

The line features a LA-455 two-cables per phase design with two optical ground wire, OPGW-type cables.

It consists of a total of 36 towers made up of metal lattice structures.